75 State Street, Boston, MA - Slurry Wall Case Study
top of page

75 State Street, Boston, MA - Slurry Wall Case Study

75 State Street, Boston, MA

75 State Street, Boston, MA - Slurry Wall Case Study

This case study is a review of published report (1).

The 75 State Street building is a 31-story office tower with six levels of below-grade space utilized primarily for parking. Permanent and construction earth support was provided by 2.5'-thick, 85'-deep diaphragm wall constructed with the slurry trench method. The 65-ft deep excavation was constructed by the top/down method, braced by 5 floor levels. The diaphragm wall extends 20' below the final excavation grade into the underlying till.

Soil conditions at the structure site are typical of the Boston area located outside the old colonial shoreline. The overburden soils consist primarily of fill, Boston Blue Clay, glacial till, and highly altered bedrock 70' to 100' below the surface. The upper 10ft to 20 ft top of the clay is an overconsolidated crust, (OCR >2). The overconsolidation ratio decreases rapidly with increasing depth as the clay becomes almost normally consolidated (OCR= 1 to 1.1).

The bedrock at the site belongs to the Cambridge Argillite formation and it is highly altered, containing zones of clay-like kaolinized material. Thickness of these clay-like "soil" zones may vary from a few inches to hundreds of feet (2).

75 State Street, Boston, MA - Slurry Wall Case Study

Many adjacent buildings exist near the site. Some of these buildings are supported on shallow foundations, while within the site a series of concrete-filled pipe piles from a previous parking garage had to be removed. The Massachusetts Bay Transit Authority Blue Line tunnel below State Street was a major concern for this project.


The diaphragm wall was designed to provide a semi-rigid wall system, thus eliminating the need for underpinning adjacent structures and provide foundation support for the perimeter columns. In addition, the diaphragm walls were incorporated into the structure and provided seepage cut off allowing the lowest floor level to be designed as a fully relieved slab-on-grade (1), since the underlying bedrock at the site has very low permeability.

Many adjacent buildings exist near the site. Some of these buildings are supported on shallow foundations, while within the site a series of concrete-filled pipe piles from a previous parking garage had to be removed. The Massachusetts Bay Transit Authority Blue Line tunnel below State Street was a major concern for this project.

The diaphragm wall was designed to provide a semi-rigid wall system, thus eliminating the need for underpinning adjacent structures and provide foundation support for the perimeter columns. In addition, the diaphragm walls were incorporated into the structure and provided seepage cut off allowing the lowest floor level to be designed as a fully relieved slab-on-grade (1), since the underlying bedrock at the site has very low permeability.

The construction process proceeded generally as planned with two exceptions (1): a) The slurry caisson method was adopted for installation of the major core column foundations after several attempts to excavate and dewater the holes failed. b) A major problem was pile extraction within the site prior to excavation. The voids created in the clay by pile extraction plus pre-excavation along the slurry wall alignment resulted in excessive inward wall movements before the floor systems could be placed. This clearly illustrated the importance of the excavation/floor slab construction sequence.


3. Performance


At 75 State Street, where up to 60 ft. of clay underlies the site, horizontal wall movements ranged from 0.5" to 2". The largest movements took place where the clay was the thickest and a two level high mechanical room existed. Adjacent buildings within 5' to 20' from the excavation settled from 1" to 4". However, 50% of this movement occurred prior to the start of excavation and can be attributed to earlier pile extraction and caisson installation. Horizontal movements were within the predicted range for an excavation of this size. However, settlements were significantly larger than predicted. 4. Reference

1. Dr. James M. Becker, Mark X. Haley, "Up/Down Construction", Design and Performance of Earth Retaining Structures, Proceedings/Geotechnical Engineering Division, Cornell University, Ithaca, New York - June 18-21, 1990 2. Humphrey, J. T., Soudemir, C.: "Special Bedrock Conditions in Greater Boston", Detection of and Construction at the Soil/Rock Interface, ASCE, Geotechnical Special Publication No. 28., 1991, pg. 45-57.


 

DeepEX Software Can Design any Deep Excavation Model in Minutes! Analyze Deep Excavations with All Methods: Limit Equilibrium - Non-Linear - Finite Element Analysis! Design Anchored Walls, Braced Excavations, Cofferdams, Deadman Wall Systems, Top-Down + more! AASHTO LRFD, CALTRANS, EUROCODES 2, 3, 7, 8, ACI, BS, Australian Codes, Chinese Codes +more!


 

Solutions for Geotechnical Engineering Professionals:


DeepEX: Deep Excavations Design Software

DeepEX: Deep Excavations Design Software




DeepFND: Pile Foundations Design Software

DeepFND: Pile Foundations Design Software




HelixPile Helical Piles Design Software

HelixPile Helical Piles Design Software




SnailPlus: Soil Nail Walls Design Software

SnailPlus: Soil Nail Walls Design Software






SELECTED POSTS:

bottom of page