|
SUPPORT SYSTEMS FOR DEEP EXCAVATION:
Top/Down Construction
Top/down or up/down construction methods are another method for
constructing deep excavations. In this case the basement floors
are constructed as the excavation progresses. The top/down method
has been used for deep excavation projects where tieback installation
was not feasible and soil movements had to be minimized. Figures
1 through 2 show construction photographs from two top/down excavations
in Boston. The general top/down construction sequence is shown
in Figure 3.. The Post Office Square Garage in Boston (7-levels
deep) is one of the best-instrumented and documented top/down
projects in the US (Whittle, et al., Whitman et al., 1991).
The sequence construction begins with retaining wall installation
and then load-bearing elements that will carry the future super-structure.
The basement columns (typically steel beams) are constructed before
any excavation takes place and rest on the load bearing elements.
These load bearing elements are typically concrete barrettes constructed
under slurry (or caissons). The top few feet of a barrette with
a steel beam can be seen in Figure 2. Then the top floor slab
is constructed with at least on construction (glory) hole left
open to allow removal of spoil material (Figs. 2, 3).
The excavation starting at the glory hole begins once the top
floor has gained sufficient strength. Soil under the top basement
floor is excavated around the basement columns to slightly lower
than the first basement floor elevation in order to allow for
the installation of the forms for the first level basement slab.
Glory holes are left open within each newly formed basement floor
slab and the procedure is repeated. Each floor rests on the basement
columns that were constructed earlier (Fig. 2).
Please click here
to find out how to DESIGN TOP/DOWN EXCAVATIONS WITH DeepXcav 2010
|